Required Inspections
The following inspections are required for each building project. Some may not apply to every project. 1 (One) day notice is required for all inspections.
- Must have portable toilet, gravel drive and erosion control before first inspection
Residential - Required Inspections
- Footing
- Plumbing under Slab
- Slab
- Site Pole
- Electrical Rough-In
- Heating and Air Rough-In
- Plumbing Rough-In
- Gas Rough-In
- Shower Pan Inspection
- Post Tie downs
- Air Barrier
- Duct Testing
- Framing (All Rough-Ins Must Pass Before Requesting The Framing Inspection)
- Insulation
- Sewer
- Temporary Power (Deposit required by homeowner)
- Driveway
- Gas Service
- Final
Commercial - Required Inspections
- Footing
- Plumbing under Slab
- Electrical under Slab
- Slab
- Site Pole
- Sprinkler Underground pressure test and Flush from vault to building - Codes
- Sprinkler Underground pressure test and Flush from main to vault - Public Works
- Sprinkler Vault installation – Public Works
- Sprinkler Vault - Codes
- Electrical Rough-In
- Heating and Air Rough-In
- Plumbing Rough-In
- Gas Rough-In
- Sprinkler 2 hr. pressure test and flush – Codes
- Sprinkler Rough in - Codes
- Fire Alarm Rough in
- Framing (All Rough-Ins Must Pass Before Requesting The Framing Inspection)
- Sewer
- Grease Trap Installation – Public Works
- Lines from Sewer to and from grease trap – Codes
- Temporary Power
- Driveway
- Gas Service
- Final: Building – Codes
- Final: Sprinkler – Codes
- Final: Fire Alarm – Codes
- Final: Grease Trap – Public Works