Required Inspections

The following inspections are required for each building project. Some may not apply to every project.  1 (One) day notice is required for all inspections.

  • Must have portable toilet, gravel drive and erosion control before first inspection

Residential - Required Inspections

  • Footing
  • Plumbing under Slab
  • Slab
  • Site Pole
  • Electrical Rough-In
  • Heating and Air Rough-In
  • Plumbing Rough-In
  • Gas Rough-In
  • Shower Pan Inspection
  • Post Tie downs
  • Air Barrier
  • Duct Testing
  • Framing (All Rough-Ins Must Pass Before Requesting The Framing Inspection)
  • Insulation
  • Sewer
  • Temporary Power (Deposit required by homeowner)
  • Driveway
  • Gas Service
  • Final

Commercial - Required Inspections

  • Footing
  • Plumbing under Slab
  • Electrical under Slab
  • Slab
  • Site Pole
  • Sprinkler Underground pressure test and Flush from vault to building - Codes
  • Sprinkler Underground pressure test and Flush from main to vault - Public Works
  • Sprinkler Vault installation – Public Works
  • Sprinkler Vault - Codes
  • Electrical Rough-In
  • Heating and Air Rough-In
  • Plumbing Rough-In
  • Gas Rough-In
  • Sprinkler 2 hr. pressure test and flush – Codes
  • Sprinkler Rough in - Codes
  • Fire Alarm Rough in
  • Framing (All Rough-Ins Must Pass Before Requesting The Framing Inspection)
  • Sewer
  • Grease Trap Installation – Public Works
  • Lines from Sewer to and from grease trap – Codes
  • Temporary Power
  • Driveway
  • Gas Service
  • Final: Building – Codes
  • Final: Sprinkler – Codes
  • Final: Fire Alarm – Codes
  • Final: Grease Trap – Public Works